All guides

Change orders and your pay application

6 min read · Updated June 2026

A change order modifies your original contract — adding or removing scope, and adjusting the price. On a progress bill, the question that trips people up is simple but important: when and howdoes a change order actually show up on your pay application? Here's the workflow.

Only approved change orders are billable

This is the rule that protects your cash flow and your relationship with the GC: you bill approved change orders, not pending ones.A change order becomes part of the contract when it's approved in writing. Until then, even if you've done the work, it isn't part of the contract sum — and putting it on a pay app will get the whole application kicked back.

Keep a running list of pending change orders so nothing gets lost, but only move them onto the bill once they're signed.

How an approved change order flows through the pay app

An approved change order touches two places:

  • G702 Line 2 — net change by change orders. The net of every approved CO (additions minus deductions) lands here and adjusts your contract sum to date on Line 3.
  • The G703 schedule of values. The scope itself goes on the continuation sheet— either as a new line item or by changing an existing line's scheduled value (Column C).

When those reconcile — your G703 scheduled-value total equals the adjusted contract sum on Line 3 — the pay app is internally consistent and the GC can approve it at a glance.

New line vs. adjusted line

Most GCs prefer change orders as new SOV lines(e.g., "CO #3 — added roof drains"). It keeps the change visible and auditable. Adjusting an existing line's scheduled value is fine for a small tweak to that exact item, but it hides the change inside the original scope — ask your GC which they want.

A quick example

Say your original contract is $200,000 and you get one approved change order for $15,000 of added work:

  • Line 1 (original contract sum): $200,000
  • Line 2 (net change by change orders): $15,000
  • Line 3 (contract sum to date): $215,000

On the G703 you add a $15,000 line (or increase the relevant line by $15,000) so the schedule of values totals $215,000 and matches Line 3. From there you bill the change-order work each period just like any other line — percent complete, retainage, and all.

Deductive change orders

A change order can also remove scope. A deductive CO is entered as a negative on Line 2, lowering your contract sum, and reduces the affected scheduled value on the G703.

Stop building pay apps in a spreadsheet

DrawFort fills in the carry-forward, computes retainage and current payment due, handles change orders, and exports a clean G702/G703 PDF your GC can approve at a glance.

Frequently asked questions

Can I bill a change order before it's approved?

No. Only bill approved change orders. Work performed under a pending or verbal change order is real, but until it's approved in writing it isn't part of the contract sum — billing it will get your pay application rejected. Track pending COs separately and add them once they're signed.

Does a change order go on the G702 or the G703?

Both. The net of all approved change orders shows on G702 Line 2 (net change by change orders), which adjusts your contract sum to date on Line 3. The actual scope is added to the G703 — either as a new line item or by adjusting an existing line's scheduled value.

Should a change order be a new SOV line or an adjustment to an existing one?

Either works; follow what your GC prefers. A new line keeps the change visible and easy to audit, which most GCs like. Adjusting an existing line is fine for small scope tweaks to that exact item.

What about deductive change orders?

A deductive change order reduces the contract sum. It's entered as a negative amount on Line 2 and lowers the affected scheduled value on the G703.

Keep reading